What happened this year
A scramble for AI ready computing pushed U.S. demand for large data centers past the available powered sites and the crews to build them. Turner & Townsend says that mismatch stretched schedules, added risk for contractors, and lifted costs 13% from a year ago.
That increase was more than twice the global pace and roughly triple the average annual rise over the past decade. The findings come from more than 500 active or recently finished projects in 62 markets and a survey of 400 data center specialists.
Where projects hit friction
There was a bit of easing in the rate of cost inflation, but not enough to counter the jump in demand or the rush to deliver faster. As Paul Barry, who leads data center work in North America at Turner & Townsend, put it, "More aggressive schedules tie to contractors in particular and subcontractors baking in more risk allowances in their pricing." He added, "So whether that's acceleration allowances, whether that's more overtime and labor attraction allowances, even just higher fees for taking on the risk of delivering at a faster pace than what they would traditionally take on."
Those risk allowances, combined with demand spikes and supply chain strain, are showing up as higher project totals. Power remains the pivotal constraint: 56% of respondents flagged it as a major obstacle. A narrow majority said utility connections typically take around one to two years, and close to one third said they take longer than two years.
When complex infrastructure and finance intersect, staying informed matters, so sign up for the free Market Briefs newsletter that saves time
Power connection costs differ by market. On a representative 60 megawatt design, Silicon Valley comes in at $15.01 per watt, while Dallas is $10.51. Labor is another headwind across U.S. construction, and only a little more than one quarter of those surveyed said contractor capacity to handle backlogs is adequate.
What this means for your portfolio
Spending signals remain large and long dated. According to a recent PwC report, global data center capital expenditure stands at about $800 billion this year and is projected to hit $1.8 trillion per year by 2050; the U.S., it adds, is likely to make up nearly half of overall AI infrastructure outlays, covering data centers and chips alike.
Looking nearer term, Barry expects cost increases to settle into the 6% to 10% range over the next year, noting many major builds have already locked in risks within current contracts. "If this demand continues, then there'll be more continued flow of project starts and so on, but I think we've hit a big surge in 2026, especially of new big major projects that have been procured."